Time & planning / GanttProject

Stress-test a short print schedule in GanttProject

Link a proof to approval and printing, then find out what really moves when a correction costs one extra workday.

What stands out in GanttProject

In a small print run, changing the proof is inconvenient. Discovering that the printer cannot start until the change is approved is the part that moves the delivery. GanttProject's scheduler uses dependencies to calculate when linked tasks can occur. A modest plan with three real handoffs teaches more than a wall of colored bars arranged to resemble a finished calendar.

Walkthrough

  1. Create a practice project with tasks called Prepare proof, Approve proof and Print run. Enter estimated durations of two working days, one working day and two working days. Add a fourth task called Assemble mailing list. It can proceed while the designer prepares the proof, so keep it independent for the moment.
  2. Set Prepare proof as a predecessor of Approve proof with a finish-to-start relationship. Then make approval a finish-to-start predecessor of printing. Read each link as a sentence a colleague could challenge: “Printing can begin after proof approval finishes.” If these words do not reflect the actual arrangement with your printer, revise the relationship.
  3. Save a separate practice copy. Increase the proof duration from two days to three and inspect approval and printing. Record which dates move, then inspect the mailing list. If a supposedly independent task also shifts, check its predecessors and the project's working calendar before manually dragging its bar back.
  4. Check the revised dates with the people doing the work. A calculated Tuesday start is attainable only if the printer has capacity that day. Add a real scheduling constraint when one exists, and keep a written note of where it came from. A printer's confirmed slot and your preferred delivery date have different consequences.

Field tip

Before sending a pickup date, look for nonworking days between linked tasks. A one-working-day delay can span a weekend on the customer's calendar. Communicate the actual calendar date and the reason it changed.

Where it falls short

A finish-to-start link describes a dependency. It cannot confirm that a supplier accepted the job, that the design is approved or that two people will be free at the same instant. Validate those assumptions outside the chart.

Try it yourself

Add a final task called Pack mailing. It needs both printed sheets and a finished list. Make both tasks predecessors. In one practice copy extend the mailing list by a day, then by a week. Compare the point at which mailing-list preparation becomes the work that determines the packing date.